Linden Street- Salem

New Construction of Six (6) Homes

$4.7M Total Development Costs

Development partnership with The Authority to redevelop 11 vacant properties

Status of Project:

  • Executed agreement of sale with City of Salem

  • Completed predevelopment work and schematic design

  • Secured preliminary construction financing

  • Zoning approval expected September 2024

  • Construction start Spring 2025

Casas del Rio- Camden

New Construction of 13 Homes

$9.2M Total Development Costs

Sponsored by Camden Lutheran Housing Inc., financial consulting and project managing by Restrepo & Associates

Status of Project:

Spruce Fields- Bridgeton

New Construction of Five (5) Homes

$3.5M Total Development Costs

Sponsored by Gateway Community Action Partnership, financial consulting and project managing by Restrepo & Associates

Status of Project:

  • Purchased 7 private parcels completed

  • Predevelopment development and zoning approval secured

  • Secured $2M subsidy from New Jersey Department of Community Affairs (NJDCA) Affordable Housing Trust Fund (AHTF)

  • Secured preliminary construction financing

  • Construction start Fall 2024

  • Part of Southeast Gateway Neighborhood Revitalization

Esperanza Homes- New Brunswick

Rehabilitation of Two (2) Homes

$2.5M Total Development Costs

Sponsored by New Brunswick Tomorrow, financial consulting and project managing by Restrepo & Associates

Status of Project:

543 State Street- Camden

Adaptive Reuse of Historical Site for 22 New Residential Units

$9.7M Total Development Costs

Developed by Camden Lutheran Housing, Inc.; financial consulting and project management by Restrepo & Associates

Status of Project:

  • CHLI purchased property for $199,000 in June 2024; property appraised for $650,000

  • Proposed use includes 17 family units, 4,000 square feet of commercial space, and conversion of the rectory into 5 units of permeant supportive housing

  • Secured $500,000 revolving line of credit from New Jersey Community Capital for acquisition

  • Currently completing predevelopment for zoning application submission by end of 2024

  • Construction start Fall 2025

  • Part of Neighborhood Revitalization Tax Credit Program (NRTC)

Harmony House- Jersey City

New Construction of Mixed Use Building With 44 Residential Units

$14.5M Total Development Costs

Developed by Northern United International Corp., financial structuring and subsidy application by Restrepo & Associates

Status of Project:

104 and 110 Amherst Ave- East Orange

New Construction of Five (5) Rental Units on Two (2) Sites

$3.2M Total Development Costs

Sponsored by East Orange Housing and Community Development Corporation, financial consulting and project managing by Restrepo & Associates

Status of Project:

  • Sponsor has site control

  • Secured $1.4M in private financing for acquisition, predevelopment, and construction

  • Completed design and predevelopment work

  • Zoning approval expected by end of year 2024

  • Online view of neighborhood